A field change log shows this condition: a $114,000 allowance is reconciled to $137,300 actual cost. Before markup, what additive adjustment is due?
Correct Answer
B) $23,300
The calculation gives $23,300 for the stated allowance add. Other choices: the distractors come from omitting an adjustment, using the wrong rate, or applying a rounded shortcut for calculation item 268.
Why This Is the Correct Answer
The calculation gives $23,300 for the stated allowance add.
Why the Other Options Are Wrong
Option A: $20,970
allowance add, choice a: $20,970 takes one allowance-side amount as the adjustment.
Option C: $25,630
allowance add, choice c: $25,630 takes one allowance-side amount as the adjustment.
Option D: $29,125
allowance add, choice d: $29,125 takes one allowance-side amount as the adjustment.
Memory Technique
Remember allowance add as "base, adjustment, final unit"; the last unit should read $23,300.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "allowance add calculation" to confirm that The calculation gives $23,300 for the stated allowance add.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?