The estimator marks a risk item in the bid recap: what controls the deadline for a bidder to protest an award decision?
Correct Answer
B) The protest procedure stated in the procurement documents
The protest procedure stated in the procurement documents is the controlling requirement: the distractors are related-looking contract or field terms, but they do not match the cited requirement for review item 224.
Why This Is the Correct Answer
The protest procedure stated in the procurement documents is the controlling requirement
Why the Other Options Are Wrong
Option A: Measure the protest deadline from the supplier's catalog date
Choice A gives The supplier's catalog date. Its specific error: the choice would not get the project.
Option C: Measure the protest deadline from the final warranty date
In procurement and contracting, The final warranty date is the wrong selection for Bid protest timing: it points to The final warranty date, but.
Option D: Classify it as a deleted alternate
The trap in D is A deleted alternate. That selection is wrong because the option tries to substitute, waive, or delete the Bid protest timing control; the item instead requires.
Memory Technique
Link bid protest timing to its book condition; a different condition means a different answer than The protest procedure stated in the procurement documents.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Bid protest procedure" to confirm that The protest procedure stated in the procurement documents is the controlling requirement
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass