A deck installer checks the fastening plan: which term describes a bid that materially follows the bid form, addenda, security, and other bidding requirements?
Correct Answer
B) Responsive bid
Responsive bid is the controlling requirement: the distractors are related-looking contract or field terms, but they do not match the cited requirement for review item 213.
Why This Is the Correct Answer
Responsive bid is the controlling requirement
Why the Other Options Are Wrong
Option A: Responsible bidder
The trap in A is Responsible bidder. That selection is wrong because it names a financial document or payment mechanism, not the Responsive bid action/result stated by Responsive bid; A responsive bid conforms to material bidding requirements.
Option C: Unit-price underrun
Choice C (Unit-price underrun) is rejected because it answers the Responsive bid prompt with the wrong practical move.
Option D: Substantial completion
In procurement and contracting, Substantial completion is the wrong selection for Responsive bid: it leaves out the controlling Responsive bid result: Responsive bid.
Memory Technique
Make responsive bid a tabbed card: cite the exact condition, then choose Responsive bid.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Bid responsiveness" to confirm that Responsive bid is the controlling requirement
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass