For a progress-payment cutoff, which waiver is appropriate when payment has not yet cleared?
Correct Answer
A) Conditional lien waiver tied to receipt of payment
Conditional lien waiver tied to receipt of payment is the controlling requirement: the distractors are related-looking contract or field terms, but they do not match the cited requirement for review item 158.
Why This Is the Correct Answer
Conditional lien waiver tied to receipt of payment is the controlling requirement
Why the Other Options Are Wrong
Option B: Make unconditional final release before payment the answer for lien waiver
The trap in B is Unconditional final release before payment. That selection is wrong because it shifts the question into contract administration money flow.
Option C: Select bid addendum for lien waiver
Choice C gives Bid addendum. Its specific error: it names a financial document or payment mechanism, not the Lien waiver action/result stated by.
Option D: Limit lien waiver to builder's risk policy
Choice D (Builder's risk policy) is rejected because the option does not produce the required Lien waiver outcome.
Memory Technique
Make lien waiver a tabbed card: cite the exact condition, then choose Conditional lien waiver tied to receipt of payment.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Conditional lien waivers" to confirm that Conditional lien waiver tied to receipt of payment is the controlling requirement
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
