During buyout, a scope gap means:
Correct Answer
A) Required work is missing between bid packages or subcontract scopes
A scope gap exists when required work is not covered by the intended contract or subcontract scopes. Other choices describe overlap, alternate acceptance, or payment terms.
Why This Is the Correct Answer
A scope gap exists when required work is not covered by the intended contract or subcontract scopes. Other choices describe overlap, alternate acceptance, or payment terms.
Why the Other Options Are Wrong
Option B: Two subcontractors both include the same complete work
In procurement and contracting, Two subcontractors both include the same complete work is the wrong selection for Scope gap: it leaves out the controlling Scope gap result: Required work is missing between bid packages or subcontract scopes.
Option C: The owner has accepted all alternates
The trap in C is The owner has accepted all alternates. That selection is wrong because the choice would not get the project to Required work is missing between bid packages or subcontract scopes, which is the Scope gap result verified by the source; A scope gap is required work missing from assigned contract or subcontract scopes.
Option D: Use the pay application with no retainage to close the scope gap
Choice D gives The pay application has no retainage. Its specific error: it names a financial document or payment mechanism, not the Scope gap action/result stated by Required work is missing between bid packages or subcontract scopes.
Memory Technique
Picture scope gap doing the job; the answer names that job as Required work is missing between bid packages or subcontract scopes.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Buyout scope gaps" to confirm that A scope gap exists when required work is not covered by the intended contract or subcontract scopes.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
