Retainage on a progress payment is:
Correct Answer
D) A withheld part of earned payment held under the contract until later release
Retainage is part of earned payment held back under contract terms until later release conditions are met. Other choices confuse it with bonds, taxes, or design contingency.
Why This Is the Correct Answer
Retainage is part of earned payment held back under contract terms until later release conditions are met. Other choices confuse it with bonds, taxes, or design contingency.
Why the Other Options Are Wrong
Option A: Classify the condition as a bid bond premium as a bonding paperwork issue that controls retainage
Choice A gives A bid bond premium. Its specific error: the option answers a paperwork, payment, or bonding issue.
Option B: Classify the condition as a sales tax charged on stored materials
Choice B (A sales tax charged on stored materials) is rejected because the choice would not get the project to A withheld part of earned payment held under the contract until later release, which is the Retainage result verified by the source.
Option C: Classify the condition as a design contingency owned by the architect
In procurement and contracting, A design contingency owned by the architect is the wrong selection for Retainage: the option does not produce the required Retainage outcome, A withheld part of earned payment held under the contract until later release.
Memory Technique
Keep retainage as a cause-to-effect card with A withheld part of earned payment held under the contract until later release on the back.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Retainage" to confirm that Retainage is part of earned payment held back under contract terms until later release conditions are met.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass