An RFI response clarifies that added backing is required in walls already framed. The response changes cost and schedule. What should the contractor do?
Correct Answer
C) Give required notice and process the cost or time impact under the contract change procedure
If an RFI response creates a cost or time impact, the contractor should provide required notice and process the change under the contract procedure. Other choices waive or ignore the impact or omit required work.
Why This Is the Correct Answer
If an RFI response creates a cost or time impact, the contractor should provide required notice and process the change under the contract procedure. Other choices waive or ignore the impact or omit required work.
Why the Other Options Are Wrong
Option A: Absorb the cost because every RFI is free
Choice A (Absorb the cost because every RFI is free) is rejected because it points to Absorb the cost because every RFI is free, but.
Option B: Handle rFI cost impact by choosing to proceed without notice and claim it at final payment
In procurement and contracting, Proceed without notice and claim it at final payment only is the wrong selection for RFI cost impact: it tries to bypass the RFI cost impact checkpoint.
Option D: Close contract execution first and resolve the rFI cost impact record later
Choice D gives Delete the backing from the work. Its specific error: the option tries to substitute, waive, or delete the RFI cost impact control; the item instead requires Give required notice and process the cost or time impact under the contract change procedure.
Memory Technique
Remember RFI cost impact by its jobsite consequence: the correct move points to Give required notice and process the cost or time impact under the contract change procedure.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "RFI and change notice procedures" to confirm that If an RFI response creates a cost or time impact, the contractor should provide required notice and process the change under the contract procedure.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
