NASCLAContractsmedium27% of exam part

An RFI response clarifies that added backing is required in walls already framed. The response changes cost and schedule. What should the contractor do?

Correct Answer

C) Give required notice and process the cost or time impact under the contract change procedure

If an RFI response creates a cost or time impact, the contractor should provide required notice and process the change under the contract procedure. Other choices waive or ignore the impact or omit required work.

Answer Options
A
Absorb the cost because every RFI is free
B
Handle rFI cost impact by choosing to proceed without notice and claim it at final payment
C
Give required notice and process the cost or time impact under the contract change procedure
D
Close contract execution first and resolve the rFI cost impact record later

Why This Is the Correct Answer

If an RFI response creates a cost or time impact, the contractor should provide required notice and process the change under the contract procedure. Other choices waive or ignore the impact or omit required work.

Why the Other Options Are Wrong

Option A: Absorb the cost because every RFI is free

Choice A (Absorb the cost because every RFI is free) is rejected because it points to Absorb the cost because every RFI is free, but.

Option B: Handle rFI cost impact by choosing to proceed without notice and claim it at final payment

In procurement and contracting, Proceed without notice and claim it at final payment only is the wrong selection for RFI cost impact: it tries to bypass the RFI cost impact checkpoint.

Option D: Close contract execution first and resolve the rFI cost impact record later

Choice D gives Delete the backing from the work. Its specific error: the option tries to substitute, waive, or delete the RFI cost impact control; the item instead requires Give required notice and process the cost or time impact under the contract change procedure.

Memory Technique

Remember RFI cost impact by its jobsite consequence: the correct move points to Give required notice and process the cost or time impact under the contract change procedure.

Reference Hint

Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "RFI and change notice procedures" to confirm that If an RFI response creates a cost or time impact, the contractor should provide required notice and process the change under the contract procedure.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.