Rock excavation is paid by unit price, and field quantities exceed the bid quantity. Which record best supports the payment adjustment?
Correct Answer
A) Jointly documented field measurements tied to the unit-price item
Unit-price adjustments depend on measured quantities of the defined work, so documented field measurement supports the payment change. Other choices lack the quantity basis or ignore measured overrun.
Why This Is the Correct Answer
Unit-price adjustments depend on measured quantities of the defined work, so documented field measurement supports the payment change. Other choices lack the quantity basis or ignore measured overrun.
Why the Other Options Are Wrong
Option B: Classify the condition as a lump-sum guess from the superintendent
Choice B gives A lump-sum guess from the superintendent. Its specific error: it answers the Unit-price documentation prompt with the wrong practical move.
Option C: Base the unit-price documentation response on the original bid quantity
Choice C (The original bid quantity only) is rejected because the option delays or omits the controlling step.
Option D: Classify the condition as a photo with no measured quantity
In procurement and contracting, A photo with no measured quantity is the wrong selection for Unit-price documentation: the choice would not get the project to Jointly documented field measurements tied to the unit-price item, which is the Unit-price documentation result verified by the source.
Memory Technique
Pair unit-price documentation with the real field trigger, then choose the response that produces Jointly documented field measurements tied to the unit-price item.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Unit-price measurement documentation" to confirm that Unit-price adjustments depend on measured quantities of the defined work, so documented field measurement supports the payment change.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass