A subcontractor bills for off-site stored millwork but provides no invoice, storage location, insurance evidence, or proof the material is reserved for the project. What should the payment review do?
Correct Answer
B) Withhold stored-material payment until the required documentation is provided
Stored-material payments require documentation that the materials exist, are protected, and are allocated to the project. Other choices pay without controls or misclassify the request.
Why This Is the Correct Answer
Stored-material payments require documentation that the materials exist, are protected, and are allocated to the project. Other choices pay without controls or misclassify the request.
Why the Other Options Are Wrong
Option A: Pay it because the subcontractor plans to order soon
Choice A (Pay it because the subcontractor plans to order soon) is rejected because the option answers a paperwork, payment, or bonding issue.
Option C: Resolve stored material payment after choosing to move the amount to retainage
The trap in C is Move the amount to retainage only. That selection is wrong because it tries to bypass the Stored material payment checkpoint.
Option D: The contractor should approve the full amount as a bid alternate
Choice D gives Approve the full amount as a bid alternate. Its specific error: the option answers a paperwork, payment, or bonding issue.
Memory Technique
Tag the scene with stored material payment: wrong actor or wrong timing means the fix is not Withhold stored-material payment until the required documentation is provided.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Stored-material payment controls" to confirm that Stored-material payments require documentation that the materials exist, are protected, and are allocated to the project.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass