EstatePass
NASCLAContractsmedium27% of exam part

Switchgear has a 28-week lead time, but the electrical submittal is still in draft while rough-in dates are approaching. What is the best procurement-control action?

Correct Answer

D) Escalate the submittal, approval, release, and delivery dates in the procurement log

Long-lead risk is controlled by actively managing submittal, approval, release, fabrication, and delivery dates. Other choices delay procurement or track information too late to protect the schedule.

Answer Options
A
The contractor should wait until rough-in is complete to submit
B
The contractor should track only the delivery truck number
C
The contractor should remove switchgear from the project schedule
D
Escalate the submittal, approval, release, and delivery dates in the procurement log

Why This Is the Correct Answer

Long-lead risk is controlled by actively managing submittal, approval, release, fabrication, and delivery dates. Other choices delay procurement or track information too late to protect the schedule.

Why the Other Options Are Wrong

Option A: The contractor should wait until rough-in is complete to submit

Choice A gives Wait until rough-in is complete to submit. Its specific error: the option delays or omits the controlling step.

Option B: The contractor should track only the delivery truck number

Choice B (Track only the delivery truck number) is rejected because the action skips the timing, documentation, or field-control step needed for Long-lead procurement.

Option C: The contractor should remove switchgear from the project schedule

In procurement and contracting, Remove switchgear from the project schedule is the wrong selection for Long-lead procurement: it points to Remove switchgear from the project schedule, but.

Memory Technique

Remember long-lead procurement by its jobsite consequence: the correct move points to Escalate the submittal, approval, release, and delivery dates in the procurement log.

Reference Hint

Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Long-lead procurement control" to confirm that Long-lead risk is controlled by actively managing submittal, approval, release, fabrication, and delivery dates.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.