Switchgear has a 28-week lead time, but the electrical submittal is still in draft while rough-in dates are approaching. What is the best procurement-control action?
Correct Answer
D) Escalate the submittal, approval, release, and delivery dates in the procurement log
Long-lead risk is controlled by actively managing submittal, approval, release, fabrication, and delivery dates. Other choices delay procurement or track information too late to protect the schedule.
Why This Is the Correct Answer
Long-lead risk is controlled by actively managing submittal, approval, release, fabrication, and delivery dates. Other choices delay procurement or track information too late to protect the schedule.
Why the Other Options Are Wrong
Option A: The contractor should wait until rough-in is complete to submit
Choice A gives Wait until rough-in is complete to submit. Its specific error: the option delays or omits the controlling step.
Option B: The contractor should track only the delivery truck number
Choice B (Track only the delivery truck number) is rejected because the action skips the timing, documentation, or field-control step needed for Long-lead procurement.
Option C: The contractor should remove switchgear from the project schedule
In procurement and contracting, Remove switchgear from the project schedule is the wrong selection for Long-lead procurement: it points to Remove switchgear from the project schedule, but.
Memory Technique
Remember long-lead procurement by its jobsite consequence: the correct move points to Escalate the submittal, approval, release, and delivery dates in the procurement log.
Reference Hint
Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Long-lead procurement control" to confirm that Long-lead risk is controlled by actively managing submittal, approval, release, fabrication, and delivery dates.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
