NASCLAProcurement and Contracting Requirementsmedium

An owner representative verbally asks the contractor to replace specified tile with a premium product. The work is not urgent. What should the superintendent do before ordering?

Correct Answer

A) Obtain written direction or follow the contract change process before committing the changed work

Nonurgent scope changes should follow the contract's written authorization process before the contractor commits cost or time. Other choices create unauthorized work and later payment disputes.

Answer Options
A
Obtain written direction or follow the contract change process before committing the changed work
B
Order immediately and decide price after installation
C
The superintendent should hide the substitution in the as-built drawings
D
Charge the supplier for the upgrade

Why This Is the Correct Answer

Nonurgent scope changes should follow the contract's written authorization process before the contractor commits cost or time. Other choices create unauthorized work and later payment disputes.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.