An owner representative verbally asks the contractor to replace specified tile with a premium product. The work is not urgent. What should the superintendent do before ordering?

Correct Answer

A) Obtain written direction or follow the contract change process before committing the changed work

Nonurgent scope changes should follow the contract's written authorization process before the contractor commits cost or time. Other choices create unauthorized work and later payment disputes.

Answer Options
A
Obtain written direction or follow the contract change process before committing the changed work
B
Order immediately and decide price after installation
C
The superintendent should hide the substitution in the as-built drawings
D
Charge the supplier for the upgrade

Why This Is the Correct Answer

Nonurgent scope changes should follow the contract's written authorization process before the contractor commits cost or time. Other choices create unauthorized work and later payment disputes.

Why the Other Options Are Wrong

Option B: Order immediately and decide price after installation

Choice B gives Order immediately and decide price after installation. Its specific error: the choice would not get the project to Obtain written direction or follow the contract change process before committing the changed work, which is the Oral change direction result verified by the source.

Option C: The superintendent should hide the substitution in the as-built drawings

Choice C (Hide the substitution in the as-built drawings) is rejected because it leaves the work at an informal or incomplete stage, while Oral change direction requires Obtain written direction or follow the contract change process before committing the changed work.

Option D: Charge the supplier for the upgrade

In procurement and contracting, Charge the supplier for the upgrade is the wrong selection for Oral change direction: it points to Charge the supplier for the upgrade, but.

Memory Technique

Use the phrase "problem, control, result" for oral change direction; the result side is Obtain written direction or follow the contract change process before committing the changed work.

Reference Hint

Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Change authorization procedures" to confirm that Nonurgent scope changes should follow the contract's written authorization process before the contractor commits cost or time.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.