An owner representative verbally asks the contractor to replace specified tile with a premium product. The work is not urgent. What should the superintendent do before ordering?
Correct Answer
A) Obtain written direction or follow the contract change process before committing the changed work
Nonurgent scope changes should follow the contract's written authorization process before the contractor commits cost or time. Other choices create unauthorized work and later payment disputes.
Why This Is the Correct Answer
Nonurgent scope changes should follow the contract's written authorization process before the contractor commits cost or time. Other choices create unauthorized work and later payment disputes.
Why the Other Options Are Wrong
Option B: Order immediately and decide price after installation
Choice B gives Order immediately and decide price after installation. Its specific error: the choice would not get the project to Obtain written direction or follow the contract change process before committing the changed work, which is the Oral change direction result verified by the source.
Option C: The superintendent should hide the substitution in the as-built drawings
Choice C (Hide the substitution in the as-built drawings) is rejected because it leaves the work at an informal or incomplete stage, while Oral change direction requires Obtain written direction or follow the contract change process before committing the changed work.
Option D: Charge the supplier for the upgrade
In procurement and contracting, Charge the supplier for the upgrade is the wrong selection for Oral change direction: it points to Charge the supplier for the upgrade, but.
Memory Technique
Use the phrase "problem, control, result" for oral change direction; the result side is Obtain written direction or follow the contract change process before committing the changed work.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Change authorization procedures" to confirm that Nonurgent scope changes should follow the contract's written authorization process before the contractor commits cost or time.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass