The lowest drywall proposal excludes firestopping at head-of-wall joints, while the project specifications include it in the wall assemblies. What should the general contractor do during buyout?
Correct Answer
C) Resolve the scope gap before subcontract award and carry the cost in the proper scope
Buyout should identify and close scope gaps before award so required work is included once and assigned clearly. Other choices leave a known gap, remove contract scope, or defer predictable rework.
Why This Is the Correct Answer
Buyout should identify and close scope gaps before award so required work is included once and assigned clearly. Other choices leave a known gap, remove contract scope, or defer predictable rework.
Why the Other Options Are Wrong
Option A: Carry the proposal unchanged and hope another trade covers it
In procurement and contracting, Carry the proposal unchanged and hope another trade covers it is the wrong selection for Subcontract scope gap: the choice would not get the project to Resolve the scope gap before subcontract award and carry the cost in the proper scope, which is the Subcontract scope gap result verified by the source.
Option B: The contractor should delete firestopping from the project
The trap in B is Delete firestopping from the project. That selection is wrong because it removes the controlling Subcontract scope gap requirement instead of meeting it.
Option D: The contractor should wait until final inspection to price the missing work
Choice D (Wait until final inspection to price the missing work) is rejected because the option delays or omits the controlling step.
Memory Technique
Pair subcontract scope gap with the real field trigger, then choose the response that produces Resolve the scope gap before subcontract award and carry the cost in the proper scope.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Buyout scope review" to confirm that Buyout should identify and close scope gaps before award so required work is included once and assigned clearly.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
