After bids are opened, the apparent low bidder admits its price omitted an addendum that changed door hardware. What should the procurement review focus on?
Correct Answer
B) Treat the omission as a responsiveness and scope problem under the bid instructions before award
Missing addendum scope can make a bid nonresponsive or incomplete, so the issue must be resolved under the bid instructions before award. Other choices distort the competitive basis or turn pre-award scope into an automatic extra.
Why This Is the Correct Answer
Missing addendum scope can make a bid nonresponsive or incomplete, so the issue must be resolved under the bid instructions before award. Other choices distort the competitive basis or turn pre-award scope into an automatic extra.
Why the Other Options Are Wrong
Option A: Award anyway because low price controls every defect, leaving missed addendum unverified
Choice A (Award anyway because low price controls every defect) is rejected because it leaves out the controlling Missed addendum result: Treat the omission as a responsiveness and scope problem.
Option C: Add the missing scope to the first change order automatically
The trap in C is Add the missing scope to the first change order automatically. That selection is wrong because the option answers a paperwork, payment, or bonding issue.
Option D: Ask other bidders to remove the addendum too
Choice D gives Ask other bidders to remove the addendum too. Its specific error: it shifts the question into contract administration money flow.
Memory Technique
Picture a rough-in sticker on the jobsite; missed addendum is solved by the action that leads to Treat the omission as a responsiveness and scope problem under the bid instructions before award.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Bid responsiveness and addenda" to confirm that Missing addendum scope can make a bid nonresponsive or incomplete, so the issue must be resolved under the bid instructions before award.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass