Record drawings are most useful because they:
Correct Answer
A) Show installed conditions and field changes for future operation, maintenance, and renovation
Record drawings document installed conditions and field changes, giving the owner useful information for future operation and work. Other choices confuse record drawings with payment, warranty, or bonding documents.
Why This Is the Correct Answer
Record drawings document installed conditions and field changes, giving the owner useful information for future operation and work. Other choices confuse record drawings with payment, warranty, or bonding documents.
Why the Other Options Are Wrong
Option B: The contractor should replace every payment application and treat the neighboring item as controlling record drawings
In procurement and contracting, Replace every payment application is the wrong selection for Record drawings: the option tries to substitute, waive, or delete the Record drawings control; the item instead requires Show installed conditions and field changes for future operation, maintenance, and renovation.
Option C: Make eliminate all warranties the answer for record drawings, leaving record drawings unverified
The trap in C is Eliminate all warranties. That selection is wrong because it removes the controlling Record drawings requirement instead of meeting it.
Option D: Use the bid bond to close record drawings
Choice D gives Serve as the bid bond. Its specific error: it names a financial document or payment mechanism, not the Record drawings action/result stated by Show installed conditions and field changes for future operation, maintenance, and renovation.
Memory Technique
Keep record drawings as a cause-to-effect card with Show installed conditions and field changes for future operation, maintenance, and renovation on the back.
Reference Hint
Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Record drawings concept" to confirm that Record drawings document installed conditions and field changes, giving the owner useful information for future operation and work.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
