A certificate of insurance is primarily used to:
Correct Answer
B) Evidence insurance coverage information requested by the contract
A certificate of insurance provides evidence of coverage information required by the contract. Other choices give it roles unrelated to insurance evidence.
Why This Is the Correct Answer
A certificate of insurance provides evidence of coverage information required by the contract. Other choices give it roles unrelated to insurance evidence.
Why the Other Options Are Wrong
Option A: The contractor should approve all shop drawings
Choice A gives Approve all shop drawings. Its specific error: it leaves out the controlling Certificate of insurance result: Evidence insurance coverage information requested by the contract.
Option C: The contractor should replace the signed subcontract
In procurement and contracting, Replace the signed subcontract is the wrong selection for Certificate of insurance: it treats Certificate of insurance as optional.
Option D: Make calculate liquidated damages the answer for certificate of insurance
The trap in D is Calculate liquidated damages. That selection is wrong because it points to Calculate liquidated damages, but.
Memory Technique
Make certificate of insurance a purpose cue; if the choice changes the purpose, it cannot be Evidence insurance coverage information requested by the contract.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Certificate of insurance concept" to confirm that A certificate of insurance provides evidence of coverage information required by the contract.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
