A supplier priced materials assuming a project tax exemption, but no exemption certificate has been issued. What should procurement confirm before purchase?
Correct Answer
D) Whether the tax exemption applies and what documentation is required
Procurement should confirm whether tax exemption applies and what documentation is required before relying on tax-free pricing. Other choices are unrelated to tax basis and purchasing documentation.
Why This Is the Correct Answer
Procurement should confirm whether tax exemption applies and what documentation is required before relying on tax-free pricing. Other choices are unrelated to tax basis and purchasing documentation.
Why the Other Options Are Wrong
Option A: Base the tax exemption certificate response on the supplier's preferred payment day only
In procurement and contracting, Only the supplier's preferred payment day is the wrong selection for Tax exemption certificate: the action skips the timing, documentation, or field-control step needed for Tax exemption certificate.
Option B: Accept the price information as submitted and leave tax exemption certificate unverified
The trap in B is That the punch list is closed. That selection is wrong because the choice would not get the project to Whether the.
Option C: Verify that the bid bond is released although the file does not verify tax exemption certificate
Choice C gives That the bid bond is released. Its specific error: it names a financial document or payment mechanism, not the Tax exemption certificate action/result stated by Whether the.
Memory Technique
Remember tax exemption certificate by its jobsite consequence: the correct move points to Whether the tax exemption applies and what documentation is required.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Tax exemption documentation in procurement" to confirm that Procurement should confirm whether tax exemption applies and what documentation is required before relying on tax-free pricing.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
