The owner wants to occupy the first floor while upper floors remain under construction. What contract issue should be addressed before occupancy?
Correct Answer
B) The effect on responsibility, insurance, security, warranties, and substantial completion for the occupied portion
Partial occupancy should address risk allocation, insurance, safety, security, warranty, and completion status for the occupied area. Other choices ignore the contract effects of shared use.
Why This Is the Correct Answer
Partial occupancy should address risk allocation, insurance, safety, security, warranty, and completion status for the occupied area. Other choices ignore the contract effects of shared use.
Why the Other Options Are Wrong
Option A: Address only the final bid tab for the occupied floor and leave partial occupancy unchecked
Choice A (Only the final bid tab) is rejected because it tries to bypass the Partial occupancy checkpoint.
Option C: Address only a tenant move-in memo without insurance or warranty terms
The trap in C is Only the subcontractor's logo placement. That selection is wrong because the option delays or omits the controlling step.
Option D: Hold a new bid opening for already completed work
Choice D gives A new bid opening for completed work. Its specific error: the option answers a paperwork, payment, or bonding issue.
Memory Technique
Use the phrase "problem, control, result" for partial occupancy; the result side is The effect on responsibility, insurance, security, warranties, and substantial completion for the occupied portion.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management - Basic, 14th Ed.; use by topic index - procurement and contracting fallback to confirm that Partial occupancy should address risk allocation, insurance, safety, security, warranty, and completion status for the occupied area.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
