Several underground conduit reroutes were made, but the record drawings still show the original alignment. What should be corrected before closeout?
Correct Answer
D) Update the record drawings to show the installed reroutes
Record drawings should document installed conditions, especially concealed reroutes. Other choices defeat the owner's future maintenance and renovation use.
Why This Is the Correct Answer
Record drawings should document installed conditions, especially concealed reroutes. Other choices defeat the owner's future maintenance and renovation use.
Why the Other Options Are Wrong
Option A: Wait until a future tenant improvement discovers the reroute
The trap in A is Wait until a future tenant improvement discovers the reroute. That selection is wrong because the option delays or omits the controlling step.
Option B: Submit the original bid plan as the as-built record
Choice B gives Submit the original bid plan as the as-built record. Its specific error: it names a financial document or payment mechanism, not the Record drawings not current action/result stated by Update the record drawings to show the installed reroutes.
Option C: Remove all conduit from the closeout package
Choice C (Remove all conduit from the closeout package) is rejected because the option does not produce the required Record drawings not current outcome, Update the record drawings to show the installed reroutes.
Memory Technique
Picture a tab on the jobsite; record drawings not current is solved by the action that leads to Update the record drawings to show the installed reroutes.
Reference Hint
Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Record drawing updates" to confirm that Record drawings should document installed conditions, especially concealed reroutes.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass