A subcontractor's certificate of insurance expired last month, and its crew is scheduled to mobilize tomorrow. What should the project team require before work starts?
Correct Answer
D) Obtain current evidence of required insurance coverage
Current evidence of required insurance should be obtained before the subcontractor starts work. Other choices accept stale coverage evidence or remove a contract requirement without authorization.
Why This Is the Correct Answer
Current evidence of required insurance should be obtained before the subcontractor starts work. Other choices accept stale coverage evidence or remove a contract requirement without authorization.
Why the Other Options Are Wrong
Option A: Mobilize first and ask for insurance at final payment
In procurement and contracting, Mobilize first and ask for insurance at final payment is the wrong selection for Expired insurance certificate: the option answers a paperwork, payment, or bonding issue.
Option B: Accept the expired certificate because it once existed
The trap in B is Accept the expired certificate because it once existed. That selection is wrong because it answers the Expired insurance certificate prompt with the wrong practical move.
Option C: Delete the insurance requirement from the subcontract
Choice C gives Delete the insurance requirement from the subcontract. Its specific error: it treats Expired insurance certificate as optional.
Memory Technique
Tag the scene with expired insurance certificate: wrong actor or wrong timing means the fix is not Obtain current evidence of required insurance coverage.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Insurance certificate before mobilization" to confirm that Current evidence of required insurance should be obtained before the subcontractor starts work.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass