A low bidder's price is complete, but its qualification file shows no similar project experience and insufficient bonding capacity. What should the owner evaluate?
Correct Answer
B) Whether the bidder is responsible and capable of performing the work
A complete price may still require responsibility review for experience, capacity, and resources. Other choices focus on bid receipt or closeout rather than bidder capability.
Why This Is the Correct Answer
A complete price may still require responsibility review for experience, capacity, and resources. Other choices focus on bid receipt or closeout rather than bidder capability.
Why the Other Options Are Wrong
Option A: Base the bidder responsibility concern response on whether the bid arrived in a sealed envelope only
Choice A gives Only whether the bid arrived in a sealed envelope. Its specific error: the action skips the timing, documentation, or field-control step needed for Bidder responsibility concern.
Option C: Use a later change request to handle bidder responsibility concern after award
In procurement and contracting, Whether all punch-list items are finished is the wrong selection for Bidder responsibility concern: it leaves out the controlling Bidder responsibility concern result: Whether the bidder is responsible and capable of performing the work.
Option D: Whether final retainage can be released
The trap in D is Whether final retainage can be released. That selection is wrong because it names a financial document or payment mechanism, not the Bidder responsibility concern action/result stated by Whether the bidder is responsible and capable of performing the work; A bidder may be low and responsive but still subject to responsibility review.
Memory Technique
Use the phrase "problem, control, result" for bidder responsibility concern; the result side is Whether the bidder is responsible and capable of performing the work.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Bidder responsibility review" to confirm that A complete price may still require responsibility review for experience, capacity, and resources.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?