EstatePass
NASCLAContractsmedium27% of exam part

A custom elevator controller is planned to arrive on day 76 and is needed for installation on day 89. How much procurement float exists?

Correct Answer

A) 13 days

Procurement float is required date minus planned arrival date: 89 - 76 = 13 days. Other choices subtract unrelated dates or use unsupported cushions.

Answer Options
A
13 days
B
7 days
C
11 days
D
21 days

Why This Is the Correct Answer

Procurement float is required date minus planned arrival date: 89 - 76 = 13 days. Other choices subtract unrelated dates or use unsupported cushions.

Why the Other Options Are Wrong

Option B: 7 days

procurement float, choice a: 7 days is wrong because 7 days uses the wrong side of the schedule subtraction or omits one duration component.

Option C: 11 days

procurement float, choice b: 11 days uses the wrong side of the schedule subtraction or omits one duration component.

Option D: 21 days

procurement float, choice d: 21 days is wrong because 21 days uses the wrong side of the schedule subtraction or omits one duration component.

Memory Technique

Store procurement float with its last math move; nearby answers are usually unfinished versions of 13 days.

Reference Hint

Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Procurement float calculation" to confirm that Procurement float is required date minus planned arrival date: 89 - 76 = 13 days.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.