A custom elevator controller is planned to arrive on day 76 and is needed for installation on day 89. How much procurement float exists?
Correct Answer
A) 13 days
Procurement float is required date minus planned arrival date: 89 - 76 = 13 days. Other choices subtract unrelated dates or use unsupported cushions.
Why This Is the Correct Answer
Procurement float is required date minus planned arrival date: 89 - 76 = 13 days. Other choices subtract unrelated dates or use unsupported cushions.
Why the Other Options Are Wrong
Option B: 7 days
procurement float, choice a: 7 days is wrong because 7 days uses the wrong side of the schedule subtraction or omits one duration component.
Option C: 11 days
procurement float, choice b: 11 days uses the wrong side of the schedule subtraction or omits one duration component.
Option D: 21 days
procurement float, choice d: 21 days is wrong because 21 days uses the wrong side of the schedule subtraction or omits one duration component.
Memory Technique
Store procurement float with its last math move; nearby answers are usually unfinished versions of 13 days.
Reference Hint
Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Procurement float calculation" to confirm that Procurement float is required date minus planned arrival date: 89 - 76 = 13 days.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass