Substantial completion is 12 days after the original date, but a 5-day time extension is approved. Liquidated damages are $2,400/day. What liquidated damages amount remains?

Correct Answer

D) $16,800

Compensable late days after the approved extension are 12 - 5 = 7 days. Liquidated damages are 7 x $2,400 = $16,800. Other choices use five, twelve, or seventeen days.

Answer Options
A
$12,000
B
$28,800
C
$40,800
D
$16,800

Why This Is the Correct Answer

Compensable late days after the approved extension are 12 - 5 = 7 days. Liquidated damages are 7 x $2,400 = $16,800. Other choices use five, twelve, or seventeen days.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.