NASCLAProcurement and Contracting Requirementsmedium

A contract has $54,000 of retainage held on a completed phase. The owner releases 60 percent of that retainage. How much retainage remains held?

Correct Answer

D) $21,600

Released retainage is $54,000 x 60% = $32,400, so remaining retainage is $54,000 - $32,400 = $21,600. Other choices release half, report released retainage, or leave the full amount.

Answer Options
A
$27,000
B
$32,400
C
$54,000
D
$21,600

Why This Is the Correct Answer

Released retainage is $54,000 x 60% = $32,400, so remaining retainage is $54,000 - $32,400 = $21,600. Other choices release half, report released retainage, or leave the full amount.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.