A contract clause requires written notice of claims within a stated number of days after the event. What does that clause primarily control?
Correct Answer
B) The timing and form required to preserve a claim
A claim-notice clause controls when and how notice must be given to preserve the claim under the contract. Other choices are unrelated project administration details.
Why This Is the Correct Answer
A claim-notice clause controls when and how notice must be given to preserve the claim under the contract. Other choices are unrelated project administration details.
Why the Other Options Are Wrong
Option A: Select the color of project signage for claim notice
Choice A gives The color of project signage. Its specific error: it leaves out the controlling Claim notice result: The timing and form required to preserve a claim.
Option C: Select the room numbering system for claim notice
In procurement and contracting, The room numbering system is the wrong selection for Claim notice: the option does not produce the required Claim notice outcome, The timing and form required to preserve a claim.
Option D: Base the claim notice response on the supplier's catalog format
The trap in D is The supplier's catalog format. That selection is wrong because it points to The supplier's catalog format, but.
Memory Technique
Make claim notice a tabbed card: cite the exact condition, then choose The timing and form required to preserve a claim.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management - Basic, 14th Ed.; use by topic index - liquidated damages / delay / claim notice to confirm that A claim-notice clause controls when and how notice must be given to preserve the claim under the contract.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
