The contract requires operation and maintenance manuals before final payment. What should those manuals provide?
Correct Answer
D) Manufacturer, operation, maintenance, parts, and warranty information required for installed systems
O&M manuals provide required operation, maintenance, parts, manufacturer, and warranty information for installed systems. Other choices are bidding or administrative fragments, not closeout manuals.
Why This Is the Correct Answer
O&M manuals provide required operation, maintenance, parts, manufacturer, and warranty information for installed systems. Other choices are bidding or administrative fragments, not closeout manuals.
Why the Other Options Are Wrong
Option A: The contractor should provide only the bid tab and approved schedule of values
The trap in A is Only the bid tab. That selection is wrong because it tries to bypass the O&M manuals checkpoint.
Option B: Accept the price information as submitted and leave o&M manuals unverified
Choice B gives Only the punch-list cover sheet. Its specific error: it leaves the work at an informal or incomplete stage, while O&M manuals requires Manufacturer, operation, maintenance, parts, and warranty information required for installed systems.
Option C: The contractor should provide only subcontractor contact names without operation or warranty data
Choice C (Only the subcontractor's logo) is rejected because the option delays or omits the controlling step.
Memory Technique
File O&M manuals under a warning sign: condition first, number or duty second, answer Manufacturer, operation, maintenance, parts, and warranty information required for installed systems.
Reference Hint
Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Operation and maintenance manuals" to confirm that O&M manuals provide required operation, maintenance, parts, manufacturer, and warranty information for installed systems.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass