Closeout requirements call for record drawings marked with field changes. What is the purpose of those drawings?
Correct Answer
C) To document the installed work and field changes for the owner's future use
Record drawings document the installed conditions and field changes for the owner's operation and future work. Other choices confuse record drawings with change authorization, O&M manuals, or bidding.
Why This Is the Correct Answer
Record drawings document the installed conditions and field changes for the owner's operation and future work. Other choices confuse record drawings with change authorization, O&M manuals, or bidding.
Why the Other Options Are Wrong
Option A: Use record drawings to replace every approved change order
In procurement and contracting, To replace every approved change order is the wrong selection for Record drawings: the option tries to substitute, waive, or delete the Record drawings control; the item instead requires To document the installed work and field changes for the owner's future use.
Option B: Use record drawings to delete the operation manuals
The trap in B is To delete the operation manuals. That selection is wrong because it removes the controlling Record drawings requirement instead of meeting it.
Option D: Use record drawings to reopen the bidding period, leaving record drawings unverified
Choice D (To reopen the bidding period) is rejected because the option answers a paperwork, payment, or bonding issue.
Memory Technique
Treat record drawings like a labeled shelf; only the matching condition belongs with To document the installed work and field changes for the owner's future use.
Reference Hint
Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Record drawings at closeout" to confirm that Record drawings document the installed conditions and field changes for the owner's operation and future work.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
