A project insurance schedule requires property coverage for the work while it is under construction. Which coverage is usually associated with that risk?
Correct Answer
B) Builder's risk insurance
Builder's risk insurance is property coverage for the project work during construction. Other choices are bid security, payment release, or authorization documents.
Why This Is the Correct Answer
Builder's risk insurance is property coverage for the project work during construction. Other choices are bid security, payment release, or authorization documents.
Why the Other Options Are Wrong
Option A: Select bid bond for builder's risk
The trap in A is Bid bond. That selection is wrong because it shifts the question into contract administration money flow.
Option C: Make final lien waiver the answer for builder's risk
Choice C (Final lien waiver) is rejected because the option tries to substitute, waive, or delete the Builder's risk control; the item instead requires Builder's risk insurance. The cited answer is Builder's risk insurance.
Option D: Base the builder's risk response on notice to proceed
In procurement and contracting, Notice to proceed is the wrong selection for Builder's risk: it leaves out the controlling Builder's risk result: Builder's risk insurance.
Memory Technique
Make builder's risk a tabbed card: cite the exact condition, then choose Builder's risk insurance.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Builder's risk insurance" to confirm that Builder's risk insurance is property coverage for the project work during construction.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass