The bid form contains blanks for acknowledging each addendum number. What should a bidder do before submitting the bid?
Correct Answer
D) List the issued addenda as required and include their scope in the bid
If the bid form requires addenda acknowledgment, the bidder should list issued addenda and include their scope. Other choices omit required bidding information or selectively ignore issued documents.
Why This Is the Correct Answer
If the bid form requires addenda acknowledgment, the bidder should list issued addenda and include their scope. Other choices omit required bidding information or selectively ignore issued documents.
Why the Other Options Are Wrong
Option A: The bidder should leave all blanks empty to avoid responsibility
Choice A gives Leave all blanks empty to avoid responsibility. Its specific error: the option does not produce the required Addenda acknowledgment outcome, List the issued addenda as required and include their scope in the bid.
Option B: The bidder should acknowledge only addenda that lower the price
Choice B (Acknowledge only addenda that lower the price) is rejected because it tries to bypass the Addenda acknowledgment checkpoint.
Option C: Handle addenda acknowledgment by choosing to attach the subcontractor bid only
In procurement and contracting, Attach the subcontractor bid only is the wrong selection for Addenda acknowledgment: it leaves the work at an informal or incomplete stage, while Addenda acknowledgment requires List the issued addenda as required and include their scope in the bid.
Memory Technique
Use a switch memory cue for addenda acknowledgment: the stem's condition unlocks List the issued addenda as required and include their scope in the bid.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Addenda acknowledgment on bid form" to confirm that If the bid form requires addenda acknowledgment, the bidder should list issued addenda and include their scope.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
On the window plan, locate window W91; then use the window schedule. What opening is listed?
Next Question
A wall cladding crew starts above a low roof before the base flashing and counterflashing are installed. Water will shed from the wall onto that roof edge. What is the best correction?