A procurement checklist asks whether the apparent low bidder has the experience, capacity, financial strength, and required license to perform the work. Which bidder-review concept is being checked?
Correct Answer
A) Responsibility of the bidder
Responsibility concerns the bidder's ability and qualifications to perform the work. Other choices address arithmetic, optional bid items, or closeout rather than bidder capability.
Why This Is the Correct Answer
Responsibility concerns the bidder's ability and qualifications to perform the work. Other choices address arithmetic, optional bid items, or closeout rather than bidder capability.
Why the Other Options Are Wrong
Option B: Base the responsible bidder response on mathematical extension
In procurement and contracting, Mathematical extension only is the wrong selection for Responsible bidder: it leaves the work at an informal or incomplete stage, while Responsible bidder requires Responsibility of the bidder.
Option C: Classify the condition as a voluntary alternate
The trap in C is A voluntary alternate. That selection is wrong because it points to A voluntary alternate, but.
Option D: Select final completion for responsible bidder
Choice D gives Final completion. Its specific error: it answers the Responsible bidder prompt with the wrong practical move.
Memory Technique
File responsible bidder under a tab: condition first, number or duty second, answer Responsibility of the bidder.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Bidder responsibility" to confirm that Responsibility concerns the bidder's ability and qualifications to perform the work.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass