A responsive bid is one that:
Correct Answer
C) Conforms to the material requirements of the bidding documents
A responsive bid conforms to the material requirements of the bidding documents. Other choices confuse responsiveness with contractor size, lateness, or voluntary extras.
Why This Is the Correct Answer
A responsive bid conforms to the material requirements of the bidding documents. Other choices confuse responsiveness with contractor size, lateness, or voluntary extras.
Why the Other Options Are Wrong
Option A: Base the responsive bid response on contains every possible voluntary alternate
Choice A gives Contains every possible voluntary alternate. Its specific error: it leaves out the controlling Responsive bid result: C.
Option B: Base the responsive bid response on comes from the largest contractor
Choice B (Comes from the largest contractor only) is rejected because it tries to bypass the Responsive bid checkpoint.
Option D: Select is submitted after bid opening for responsive bid
The trap in D is Is submitted after bid opening. That selection is wrong because it shifts the question into contract administration money flow.
Memory Technique
Attach responsive bid to a weep path: remember the function, then the wording Conforms to the material requirements of the bidding documents.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Responsive bid concept" to confirm that A responsive bid conforms to the material requirements of the bidding documents.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass