A project manager wants to charge rework caused by a subcontractor's installation error to the owner's contingency. What should happen first?
Correct Answer
B) Review the GMP and contingency terms to determine whether that use is allowed
Contingency use depends on the GMP and contract terms; subcontractor-caused rework may not be an allowable owner contingency use. Other choices misclassify the cost.
Why This Is the Correct Answer
Contingency use depends on the GMP and contract terms; subcontractor-caused rework may not be an allowable owner contingency use. Other choices misclassify the cost.
Why the Other Options Are Wrong
Option A: Charge it immediately because every rework item is an owner contingency cost
The trap in A is Charge it immediately because every rework item is an owner contingency cost. That selection is wrong because it leaves out the controlling Contingency use dispute result: Review the GMP and contingency terms to determine whether that use is allowed.
Option C: The contractor should hide the cost in stored materials
Choice C (Hide the cost in stored materials) is rejected because the action skips the timing, documentation, or field-control step needed for Contingency use dispute.
Option D: Convert the error into a weather delay, leaving contingency use dispute unverified
In procurement and contracting, Convert the error into a weather delay is the wrong selection for Contingency use dispute: it points to Convert the error into a weather delay, but.
Memory Technique
Remember contingency use dispute by its jobsite consequence: the correct move points to Review the GMP and contingency terms to determine whether that use is allowed.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "GMP contingency use review" to confirm that Contingency use depends on the GMP and contract terms; subcontractor-caused rework may not be an allowable owner contingency use.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass