The contractor's first schedule of values assigns nearly all profit to early demolition, leaving later finish work undervalued. What should the reviewer request?
Correct Answer
D) A revised schedule of values that reasonably allocates value to the work
A front-loaded schedule of values should be revised so payment values reasonably reflect the work. Other choices ignore payment control or request unrelated documents.
Why This Is the Correct Answer
A front-loaded schedule of values should be revised so payment values reasonably reflect the work. Other choices ignore payment control or request unrelated documents.
Why the Other Options Are Wrong
Option A: Classify the condition as a bid bond from every supplier
In procurement and contracting, A bid bond from every supplier is the wrong selection for Front-loaded SOV: the option answers a paperwork, payment, or bonding issue.
Option B: Select immediate final payment for front-loaded SOV
The trap in B is Immediate final payment. That selection is wrong because it shifts the question into contract administration money flow.
Option C: Classify the condition as a deleted construction schedule
Choice C gives A deleted construction schedule. Its specific error: it treats Front-loaded SOV as optional.
Memory Technique
Use the phrase "problem, control, result" for front-loaded SOV; the result side is A revised schedule of values that reasonably allocates value to the work.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Schedule of values front loading" to confirm that A front-loaded schedule of values should be revised so payment values reasonably reflect the work.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass