EstatePass
NASCLAProcurement and Contracting Requirementsmedium

The contractor's first schedule of values assigns nearly all profit to early demolition, leaving later finish work undervalued. What should the reviewer request?

Correct Answer

D) A revised schedule of values that reasonably allocates value to the work

A front-loaded schedule of values should be revised so payment values reasonably reflect the work. Other choices ignore payment control or request unrelated documents.

Answer Options
A
Classify the condition as a bid bond from every supplier
B
Select immediate final payment for front-loaded SOV
C
Classify the condition as a deleted construction schedule
D
A revised schedule of values that reasonably allocates value to the work

Why This Is the Correct Answer

A front-loaded schedule of values should be revised so payment values reasonably reflect the work. Other choices ignore payment control or request unrelated documents.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.