A subcontractor performs directed force-account work but waits three weeks to submit unsigned daily tickets. What problem does this create?
Correct Answer
D) The cost record is weaker because labor, equipment, and material were not verified daily
Force-account work is best supported by timely signed daily records; late unsigned tickets are harder to verify. Other choices overstate or change the payment basis without support.
Why This Is the Correct Answer
Force-account work is best supported by timely signed daily records; late unsigned tickets are harder to verify. Other choices overstate or change the payment basis without support.
Why the Other Options Are Wrong
Option A: Unsigned late tickets are stronger than daily signed records, leaving force-account signature unverified
Choice A (Unsigned late tickets are stronger than daily signed records) is rejected because it leaves out the controlling Force-account signature result: The cost record is weaker because labor, equipment, and material were not verified daily.
Option B: The work automatically becomes lump sum, leaving force-account signature unverified
In procurement and contracting, The work automatically becomes lump sum is the wrong selection for Force-account signature: the choice would not get the project to The cost record is weaker because labor, equipment, and material were not verified daily, which is the Force-account signature result verified by the source.
Option C: The owner must accept every hour without review
The trap in C is The owner must accept every hour without review. That selection is wrong because it leaves the work at an informal or incomplete stage, while Force-account signature requires The cost record is weaker because labor, equipment, and material were not verified daily; Force-account work should be documented with timely signed daily records.
Memory Technique
Pair force-account signature with the real field trigger, then choose the response that produces The cost record is weaker because labor, equipment, and material were not verified daily.
Reference Hint
Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Force-account ticket verification" to confirm that Force-account work is best supported by timely signed daily records; late unsigned tickets are harder to verify.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
