A proposed equal lighting fixture is reviewed and rejected because it lacks the specified emergency driver. What should happen before procurement continues?
Correct Answer
B) Procure the specified fixture or submit another compliant substitution for approval
After a proposed equal is rejected, the contractor should procure the specified item or obtain approval of a compliant substitution. Other choices buy nonconforming work or skip required life-safety scope.
Why This Is the Correct Answer
After a proposed equal is rejected, the contractor should procure the specified item or obtain approval of a compliant substitution. Other choices buy nonconforming work or skip required life-safety scope.
Why the Other Options Are Wrong
Option A: Order the rejected fixture to save lead time
The trap in A is Order the rejected fixture to save lead time. That selection is wrong because it answers the Rejected equal product prompt with the wrong practical move.
Option C: The contractor should remove emergency lighting from the contract, leaving rejected equal product unverified
Choice C (Remove emergency lighting from the contract) is rejected because the choice would not get the project to Procure the specified fixture or submit another compliant substitution for approval, which is the Rejected equal product result verified by the source.
Option D: Treat the rejection as an owner-caused delay without notice
In procurement and contracting, Treat the rejection as an owner-caused delay without notice is the wrong selection for Rejected equal product: it tries to bypass the Rejected equal product checkpoint.
Memory Technique
Tag the scene with rejected equal product: wrong actor or wrong timing means the fix is not Procure the specified fixture or submit another compliant substitution for approval.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Substitution rejection and procurement" to confirm that After a proposed equal is rejected, the contractor should procure the specified item or obtain approval of a compliant substitution.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass