A supplier asks for a steel price increase after award, but the subcontract has no escalation clause and the material was not changed. What should the contractor review first?
Correct Answer
A) Whether the subcontract gives entitlement to the requested price adjustment
Without a change or escalation clause, entitlement to a price increase depends on the subcontract terms. Other choices do not address contractual entitlement.
Why This Is the Correct Answer
Without a change or escalation clause, entitlement to a price increase depends on the subcontract terms. Other choices do not address contractual entitlement.
Why the Other Options Are Wrong
Option B: Review whether market prices changed after the subcontract was signed
The trap in B is The supplier's preferred color chart. That selection is wrong because it answers the Escalation clause absent prompt with the wrong practical move.
Option C: Review whether the bid bond can be amended to cover a steel price increase
Choice C gives A new bid bond form. Its specific error: the option answers a paperwork, payment, or bonding issue.
Option D: Accept the price information as submitted
Choice D (The punch-list format) is rejected because the choice would not get the project to Whether the subcontract gives entitlement to the requested price adjustment, which is the Escalation clause absent result verified by the source.
Memory Technique
Remember escalation clause absent by its jobsite consequence: the correct move points to Whether the subcontract gives entitlement to the requested price adjustment.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Escalation entitlement review" to confirm that Without a change or escalation clause, entitlement to a price increase depends on the subcontract terms.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
