A bid form shows written unit prices that do not match the bidder's extended total. The instructions say unit prices govern arithmetic extensions. What should the bid review do?
Correct Answer
C) Recalculate the extension using the governing unit prices before comparison
When bid instructions state unit prices govern, the review should recalculate extensions from those unit prices before comparison. Other choices ignore the bid instructions or move a pre-award issue into post-award changes.
Why This Is the Correct Answer
When bid instructions state unit prices govern, the review should recalculate extensions from those unit prices before comparison. Other choices ignore the bid instructions or move a pre-award issue into post-award changes.
Why the Other Options Are Wrong
Option A: The bidder should accept the highest number without checking instructions
The trap in A is Accept the highest number without checking instructions. That selection is wrong because it leaves the work at an informal or incomplete stage, while Arithmetic discrepancy requires Recalculate the extension using the governing unit prices before comparison; Bid arithmetic discrepancies should be handled according to the instructions to bidders.
Option B: Discard all unit prices and use the bidder's handwritten total only
Choice B gives Discard all unit prices and use the bidder's handwritten total only. Its specific error: the option delays or omits the controlling step.
Option D: Treat the discrepancy as an automatic change order after award
In procurement and contracting, Treat the discrepancy as an automatic change order after award is the wrong selection for Arithmetic discrepancy: it shifts the question into contract administration money flow.
Memory Technique
Picture a redline on the jobsite; arithmetic discrepancy is solved by the action that leads to Recalculate the extension using the governing unit prices before comparison.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Bid form arithmetic and governing prices" to confirm that When bid instructions state unit prices govern, the review should recalculate extensions from those unit prices before comparison.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
