A pay application includes $120,000 of approved stored material subject to 10 percent retainage. What net stored-material payment is included before previous-payment adjustments?
Correct Answer
B) $108,000
Retainage is $120,000 x 10% = $12,000, so net stored-material payment is $120,000 - $12,000 = $108,000. Other choices report retainage only, use an unsupported amount, or add retainage.
Why This Is the Correct Answer
Retainage is $120,000 x 10% = $12,000, so net stored-material payment is $120,000 - $12,000 = $108,000. Other choices report retainage only, use an unsupported amount, or add retainage.
Why the Other Options Are Wrong
Option A: $12,000
stored material retainage, choice a: $12,000 is only the retainage withheld, not the net payment.
Option C: $110,000
stored material retainage, choice c: $110,000 uses the wrong retainage base or stops before netting retainage; the.
Option D: $132,000
stored material retainage, choice d: $132,000 uses the wrong retainage base or stops before netting retainage; the.
Memory Technique
Picture a index tab labeled stored material retainage: finish every operation before accepting $108,000.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Stored material retainage" to confirm that Retainage is $120,000 x 10% = $12,000, so net stored-material payment is $120,000 - $12,000 = $108,000.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass