The procurement requirements call for escrowed bid documents after award. What is the main purpose of keeping those estimate records?
Correct Answer
B) To support later review of bid assumptions if disputes or changes arise
Escrowed bid documents preserve the estimate assumptions and backup for later review in disputes or change evaluation. Other choices misuse estimate records or override the contract documents.
Why This Is the Correct Answer
Escrowed bid documents preserve the estimate assumptions and backup for later review in disputes or change evaluation. Other choices misuse estimate records or override the contract documents.
Why the Other Options Are Wrong
Option A: Treat escrowed bid documents as replacing the contract drawings
In procurement and contracting, To replace the contract drawings is the wrong selection for Escrowed bid documents: it removes the controlling Escrowed bid documents requirement instead of meeting it.
Option C: Use escrowed bid documents to waive all change-order requirements
Choice C gives To waive all change-order requirements. Its specific error: the option tries to substitute, waive, or delete the Escrowed bid documents control; the item instead requires To support later review of bid assumptions if disputes or changes arise.
Option D: Use escrowed bid documents to hide subcontractor exclusions from the owner
Choice D (To hide subcontractor exclusions from the owner) is rejected because the option delays or omits the controlling step.
Memory Technique
Link escrowed bid documents to its book condition; a different condition means a different answer than To support later review of bid assumptions if disputes or changes arise.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Escrowed bid documents" to confirm that Escrowed bid documents preserve the estimate assumptions and backup for later review in disputes or change evaluation.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
