A product submittal includes a note excluding required accessories, but the exclusion is not accepted as a change. What is the contract effect of that note?
Correct Answer
A) It does not change the contract requirements unless processed and accepted as a contract modification
A submittal note does not modify contract scope unless the change is processed and accepted through the contract modification procedure. Other choices give the submittal an automatic change effect it does not have.
Why This Is the Correct Answer
A submittal note does not modify contract scope unless the change is processed and accepted through the contract modification procedure. Other choices give the submittal an automatic change effect it does not have.
Why the Other Options Are Wrong
Option B: Use submittal not contract modification to delete the accessories automatically
Choice B (It deletes the accessories automatically) is rejected because the option tries to substitute, waive, or delete the Submittal not contract modification control; the item instead requires It does not change the contract requirements unless processed and accepted as a contract.
Option C: Treat a submittal note as changing contract time without notice
In procurement and contracting, It changes contract time without notice is the wrong selection for Submittal not contract modification: it tries to bypass the Submittal not contract modification checkpoint.
Option D: Use submittal not contract modification to convert the work to time-and-material
The trap in D is It converts the work to time-and-material. That selection is wrong because it leaves out the controlling Submittal not contract modification result: It does not change the contract requirements unless processed and accepted as a contract modification.
Memory Technique
File submittal not contract modification under a checkpoint: condition first, number or duty second, answer It does not change the contract requirements unless processed and accepted as a contract modification.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Submittal limitations and contract modifications" to confirm that A submittal note does not modify contract scope unless the change is processed and accepted through the contract modification procedure.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
