A subcontract references the prime contract and requires the subcontractor to assume applicable prime-contract obligations for its work. What is that clause commonly intended to do?
Correct Answer
D) Flow applicable prime-contract obligations down to the subcontractor
A flow-down clause passes applicable prime-contract obligations to the subcontractor for its scope. Other choices would delete requirements or misunderstand the relationship between prime and subcontract terms.
Why This Is the Correct Answer
A flow-down clause passes applicable prime-contract obligations to the subcontractor for its scope. Other choices would delete requirements or misunderstand the relationship between prime and subcontract terms.
Why the Other Options Are Wrong
Option A: Use a later change request to handle subcontract flow-down after award
The trap in A is Delete all project specifications. That selection is wrong because it treats Subcontract flow-down as optional.
Option B: Turn the subcontract into a bid bond as a bonding paperwork issue that controls subcontract flow-down
Choice B gives Turn the subcontract into a bid bond. Its specific error: the option answers a paperwork, payment, or bonding issue.
Option C: The contractor should remove coordination duties from the subcontractor
Choice C (Remove coordination duties from the subcontractor) is rejected because the choice would not get the project to Flow applicable prime-contract obligations down to the subcontractor, which is the Subcontract flow-down result verified by the source.
Memory Technique
Treat subcontract flow-down like a labeled shelf; only the matching condition belongs with Flow applicable prime-contract obligations down to the subcontractor.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Subcontract flow-down clauses" to confirm that A flow-down clause passes applicable prime-contract obligations to the subcontractor for its scope.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
