The owner directs changed work to proceed on a force-account basis until price is settled. Which record set should be kept each day?
Correct Answer
C) Signed daily records of labor, equipment, materials, and subcontractor costs
Force-account work needs daily signed records of labor, equipment, materials, and subcontractor costs to support later pricing. Other choices do not document actual changed-work cost.
Why This Is the Correct Answer
Force-account work needs daily signed records of labor, equipment, materials, and subcontractor costs to support later pricing. Other choices do not document actual changed-work cost.
Why the Other Options Are Wrong
Option A: Base the force-account records response on the original bid form
Choice A (Only the original bid form) is rejected because it leaves the work at an informal or incomplete stage, while Force-account records requires Signed daily.
Option B: Base the force-account records response on the final lien waiver
In procurement and contracting, Only the final lien waiver is the wrong selection for Force-account records: the option delays or omits the controlling step.
Option D: Base the force-account records response on the architect's color board
Choice D gives Only the architect's color board. Its specific error: it tries to bypass the Force-account records checkpoint.
Memory Technique
Link force-account records to its book condition; a different condition means a different answer than Signed daily records of labor, equipment, materials, and subcontractor costs.
Reference Hint
Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Force-account change documentation" to confirm that Force-account work needs daily signed records of labor, equipment, materials, and subcontractor costs to support later pricing.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass