A GMP has a contractor contingency line item. What governs whether a cost may be charged to that contingency?
Correct Answer
A) The contract's contingency-use terms and required approval process
Use of contingency is governed by the contract's contingency language and required approval or reporting process. Other choices ignore the contract controls for contingency use.
Why This Is the Correct Answer
Use of contingency is governed by the contract's contingency language and required approval or reporting process. Other choices ignore the contract controls for contingency use.
Why the Other Options Are Wrong
Option B: Base the contingency authorization response on any subcontractor request without review
Choice B (Any subcontractor request without review) is rejected because it tries to bypass the Contingency authorization checkpoint.
Option C: Base the contingency authorization response on the bidder's private estimate notes
In procurement and contracting, The bidder's private estimate notes only is the wrong selection for Contingency authorization: it leaves the work at an informal or incomplete stage, while Contingency authorization requires The contract's contingency-use terms and required approval process.
Option D: Use the payment application file as the backup record for contingency authorization
The trap in D is The final punch list regardless of cause. That selection is wrong because the choice would not get the project to The contract's contingency-use terms and required approval process, which is the Contingency authorization result verified by the source; GMP contingency use is controlled by contract terms.
Memory Technique
Make contingency authorization a tabbed card: cite the exact condition, then choose The contract's contingency-use terms and required approval process.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "GMP contingency administration" to confirm that Use of contingency is governed by the contract's contingency language and required approval or reporting process.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass