A unit-price schedule states that the unit price is complete compensation for labor, material, equipment, overhead, and profit. What should the bidder include in each unit price?
Correct Answer
B) All cost components named by the unit-price requirement
If the unit-price requirement says complete compensation includes labor, material, equipment, overhead, and profit, the bidder should include those components. Other choices omit parts of the stated compensation.
Why This Is the Correct Answer
If the unit-price requirement says complete compensation includes labor, material, equipment, overhead, and profit, the bidder should include those components. Other choices omit parts of the stated compensation.
Why the Other Options Are Wrong
Option A: Limit unit price complete compensation to raw material invoices only
In procurement and contracting, Only raw material invoices is the wrong selection for Unit price complete compensation: the action skips the timing, documentation, or field-control step needed for Unit price complete compensation.
Option C: Limit unit price complete compensation to equipment fuel
Choice C gives Only equipment fuel. Its specific error: it leaves the work at an informal or incomplete stage, while Unit price complete compensation requires All cost components named by the unit-price requirement.
Option D: Base the unit price complete compensation response on the subcontractor's markup
Choice D (Only the subcontractor's markup) is rejected because the option delays or omits the controlling step.
Memory Technique
Treat unit price complete compensation like a labeled shelf; only the matching condition belongs with All cost components named by the unit-price requirement.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Unit-price bid requirements" to confirm that If the unit-price requirement says complete compensation includes labor, material, equipment, overhead, and profit, the bidder should include those components.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
