An addendum issued three days before bid opening revises the door schedule. How is that addendum treated in procurement?
Correct Answer
C) As part of the bidding and contract documents once issued
A properly issued addendum becomes part of the bidding documents and later contract documents. Other choices treat issued bid information as optional, post-award only, or bidder-specific.
Why This Is the Correct Answer
A properly issued addendum becomes part of the bidding documents and later contract documents. Other choices treat issued bid information as optional, post-award only, or bidder-specific.
Why the Other Options Are Wrong
Option A: As optional information unless the bidder likes it
Choice A (As optional information unless the bidder likes it) is rejected because it shifts the question into contract administration money flow.
Option B: Base the addendum status response on as a post-award change order
In procurement and contracting, As a post-award change order only is the wrong selection for Addendum status: it leaves the work at an informal or incomplete stage, while Addendum status requires As part of the bidding and contract documents once issued.
Option D: As a private note that only affects the low bidder
Choice D gives As a private note that only affects the low bidder. Its specific error: the action skips the timing, documentation, or field-control step needed for Addendum status.
Memory Technique
Use a rough-in sticker memory cue for addendum status: the stem's condition unlocks As part of the bidding and contract documents once issued.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Addenda as bidding documents" to confirm that A properly issued addendum becomes part of the bidding documents and later contract documents.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
