The contract requires performance and payment bonds each in the full amount of the contract sum. Which bond amount should be furnished after award?
Correct Answer
D) One hundred percent of the contract sum for each required bond
If the contract requires each bond in the full amount of the contract sum, each bond's penal sum is 100 percent of the contract amount. Other choices understate or use unrelated project amounts.
Why This Is the Correct Answer
If the contract requires each bond in the full amount of the contract sum, each bond's penal sum is 100 percent of the contract amount. Other choices understate or use unrelated project amounts.
Why the Other Options Are Wrong
Option A: Apply the Ten percent of the contract sum limit to the bond penal sum check
The trap in A is Ten percent of the contract sum. That selection is wrong because it points to Ten percent of the contract sum, but.
Option B: Base the bond penal sum response on the first month's pay application
Choice B gives Only the first month's pay application. Its specific error: it leaves the work at an informal or incomplete stage, while Bond penal sum requires One hundred percent of the contract sum for each required bond.
Option C: Base the bond penal sum response on the subcontractor's largest purchase order
Choice C (The subcontractor's largest purchase order) is rejected because it leaves out the controlling Bond penal sum result: One hundred percent of the contract sum for each required bond.
Memory Technique
Make bond penal sum a tabbed card: cite the exact condition, then choose One hundred percent of the contract sum for each required bond.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Contract bond penal sum" to confirm that If the contract requires each bond in the full amount of the contract sum, each bond's penal sum is 100 percent of the contract amount.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass