The primary protection of a payment bond is aimed at:
Correct Answer
C) Qualified labor and material claimants who are unpaid
A payment bond protects qualified labor and material claimants from nonpayment. Other choices are not the group protected by the payment bond.
Why This Is the Correct Answer
A payment bond protects qualified labor and material claimants from nonpayment. Other choices are not the group protected by the payment bond.
Why the Other Options Are Wrong
Option A: Protect only the owner against defective work after substantial completion
In procurement and contracting, The building inspector's scheduling staff is the wrong selection for Payment bond claimant: it points to The building inspector's scheduling staff, but.
Option B: Protect only the architect in design-consultant fee disputes
The trap in B is The architect's rendering consultant only. That selection is wrong because it leaves the work at an informal or incomplete stage, while Payment bond claimant requires Qualified labor and material claimants who are unpaid; Payment bonds protect qualified unpaid labor and material claimants.
Option D: The bidder who refuses to sign the contract
Choice D (The bidder who refuses to sign the contract) is rejected because the option answers a paperwork, payment, or bonding issue.
Memory Technique
Make payment bond claimant a purpose cue; if the choice changes the purpose, it cannot be Qualified labor and material claimants who are unpaid.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Payment bond claimant protection" to confirm that A payment bond protects qualified labor and material claimants from nonpayment.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
