In a GMP contract, the guaranteed maximum price is best understood as:
Correct Answer
B) A contract ceiling on payable cost and fee, subject to authorized changes
A GMP is a ceiling on the amount payable for the covered work, subject to changes allowed by the contract. Other choices confuse it with fees, bonds, or delay damages.
Why This Is the Correct Answer
A GMP is a ceiling on the amount payable for the covered work, subject to changes allowed by the contract. Other choices confuse it with fees, bonds, or delay damages.
Why the Other Options Are Wrong
Option A: Classify the condition as a minimum fee the owner must pay regardless of cost
Choice A (A minimum fee the owner must pay regardless of cost) is rejected because it names a financial document or payment mechanism, not the GMP action/result stated by A contract ceiling on payable cost and fee, subject to authorized changes.
Option C: Classify the condition as a bid bond amount as a bonding paperwork issue that controls gMP
The trap in C is A bid bond amount. That selection is wrong because it shifts the question into contract administration money flow.
Option D: Classify the condition as a daily liquidated-damages rate
Choice D gives A daily liquidated-damages rate. Its specific error: it leaves out the controlling GMP result: A contract ceiling on payable cost and fee, subject to authorized changes.
Memory Technique
Attach GMP to a redline: remember the function, then the wording A contract ceiling on payable cost and fee, subject to authorized changes.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Guaranteed maximum price concept" to confirm that A GMP is a ceiling on the amount payable for the covered work, subject to changes allowed by the contract.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
