NASCLAContractsmedium27% of exam part

A subcontractor submits a different air barrier product in a normal product-data submittal without marking it as a substitution. What should the reviewer require?

Correct Answer

A) Process it through the contract substitution procedure before accepting a product different from the specified basis

A product differing from specified requirements should be identified and reviewed through the substitution procedure. Other choices bypass contract review or omit required work.

Answer Options
A
Process it through the contract substitution procedure before accepting a product different from the specified basis
B
The reviewer should approve it silently to reduce paperwork
C
The reviewer should install first and ask for substitution approval during warranty
D
The reviewer should delete the air barrier requirement

Why This Is the Correct Answer

A product differing from specified requirements should be identified and reviewed through the substitution procedure. Other choices bypass contract review or omit required work.

Why the Other Options Are Wrong

Option B: The reviewer should approve it silently to reduce paperwork

Choice B gives Approve it silently to reduce paperwork. Its specific error: it points to Approve it silently to reduce paperwork, but.

Option C: The reviewer should install first and ask for substitution approval during warranty

Choice C (Install first and ask for substitution approval during warranty) is rejected because it answers the Submittal as substitution prompt with the wrong practical move.

Option D: The reviewer should delete the air barrier requirement

In procurement and contracting, Delete the air barrier requirement is the wrong selection for Submittal as substitution: it removes the controlling Submittal as substitution requirement instead of meeting it.

Memory Technique

Use the phrase "problem, control, result" for submittal as substitution; the result side is Process it through the contract substitution procedure before accepting a product different from the specified basis.

Reference Hint

Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Substitution and submittal procedure" to confirm that A product differing from specified requirements should be identified and reviewed through the substitution procedure.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.