A subcontractor submits a different air barrier product in a normal product-data submittal without marking it as a substitution. What should the reviewer require?
Correct Answer
A) Process it through the contract substitution procedure before accepting a product different from the specified basis
A product differing from specified requirements should be identified and reviewed through the substitution procedure. Other choices bypass contract review or omit required work.
Why This Is the Correct Answer
A product differing from specified requirements should be identified and reviewed through the substitution procedure. Other choices bypass contract review or omit required work.
Why the Other Options Are Wrong
Option B: The reviewer should approve it silently to reduce paperwork
Choice B gives Approve it silently to reduce paperwork. Its specific error: it points to Approve it silently to reduce paperwork, but.
Option C: The reviewer should install first and ask for substitution approval during warranty
Choice C (Install first and ask for substitution approval during warranty) is rejected because it answers the Submittal as substitution prompt with the wrong practical move.
Option D: The reviewer should delete the air barrier requirement
In procurement and contracting, Delete the air barrier requirement is the wrong selection for Submittal as substitution: it removes the controlling Submittal as substitution requirement instead of meeting it.
Memory Technique
Use the phrase "problem, control, result" for submittal as substitution; the result side is Process it through the contract substitution procedure before accepting a product different from the specified basis.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Substitution and submittal procedure" to confirm that A product differing from specified requirements should be identified and reviewed through the substitution procedure.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass