A subcontractor's pay application includes a large stored-material amount, but the supplier has not released the equipment for shipment or assigned it to the project. What is the payment risk?
Correct Answer
B) The request may not satisfy stored-material payment controls without evidence of project allocation and availability
Stored-material payment controls need evidence that materials exist, are allocated to the project, and are protected or available as contractually required. Other choices confuse submittal approval with payment proof.
Why This Is the Correct Answer
Stored-material payment controls need evidence that materials exist, are allocated to the project, and are protected or available as contractually required. Other choices confuse submittal approval with payment proof.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
