A subcontractor's pay application includes a large stored-material amount, but the supplier has not released the equipment for shipment or assigned it to the project. What is the payment risk?
Correct Answer
B) The request may not satisfy stored-material payment controls without evidence of project allocation and availability
Stored-material payment controls need evidence that materials exist, are allocated to the project, and are protected or available as contractually required. Other choices confuse submittal approval with payment proof.
Why This Is the Correct Answer
Stored-material payment controls need evidence that materials exist, are allocated to the project, and are protected or available as contractually required. Other choices confuse submittal approval with payment proof.
Why the Other Options Are Wrong
Option A: The owner must pay because the submittal was approved
In procurement and contracting, The owner must pay because the submittal was approved is the wrong selection for Missing supplier release: it names a financial document or payment mechanism, not the Missing supplier release action/result stated by The request may not satisfy stored-material payment controls without evidence of project allocation.
Option C: Base the missing supplier release response on stored materials never require documentation
Choice C gives Stored materials never require documentation. Its specific error: the option does not produce the required Missing supplier release outcome, The request may not satisfy stored-material payment controls without evidence of project allocation and.
Option D: The amount should be converted to liquidated damages, leaving missing supplier release unverified
Choice D (The amount should be converted to liquidated damages) is rejected because it points to The amount should be converted to liquidated damages, but.
Memory Technique
Pair missing supplier release with the real field trigger, then choose the response that produces The request may not satisfy stored-material payment controls without evidence of project allocation and availability.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Stored-material payment risk" to confirm that Stored-material payment controls need evidence that materials exist, are allocated to the project, and are protected or available as contractually required.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
