Field conditions require immediate dewatering work, and the price cannot be agreed before the pump crew mobilizes. What record should the contractor protect while proceeding under written direction?
Correct Answer
A) Daily labor, equipment, material, and subcontractor cost records for later pricing
When changed work proceeds before final pricing, detailed daily cost records support later adjustment. Other choices do not document the cost of the directed changed work.
Why This Is the Correct Answer
When changed work proceeds before final pricing, detailed daily cost records support later adjustment. Other choices do not document the cost of the directed changed work.
Why the Other Options Are Wrong
Option B: Base the unpriced change work response on the original bid recap
In procurement and contracting, Only the original bid recap is the wrong selection for Unpriced change work: the option delays or omits the controlling step.
Option C: Classify the condition as a blank warranty form
The trap in C is A blank warranty form. That selection is wrong because the choice would not get the project to Daily labor, equipment, material, and subcontractor cost records for later pricing, which is the Unpriced change work result verified by the source; Unpriced directed work should be.
Option D: Make the architect's lunch order the answer for unpriced change work
Choice D gives The architect's lunch order. Its specific error: the option does not produce the required Unpriced change work outcome, Daily labor, equipment, material, and subcontractor cost records for later pricing.
Memory Technique
Picture a field note on the jobsite; unpriced change work is solved by the action that leads to Daily labor, equipment, material, and subcontractor cost records for later pricing.
Reference Hint
Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Force-account or directed-change documentation" to confirm that When changed work proceeds before final pricing, detailed daily cost records support later adjustment.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass