Field conditions require immediate dewatering work, and the price cannot be agreed before the pump crew mobilizes. What record should the contractor protect while proceeding under written direction?

Correct Answer

A) Daily labor, equipment, material, and subcontractor cost records for later pricing

When changed work proceeds before final pricing, detailed daily cost records support later adjustment. Other choices do not document the cost of the directed changed work.

Answer Options
A
Daily labor, equipment, material, and subcontractor cost records for later pricing
B
Base the unpriced change work response on the original bid recap
C
Classify the condition as a blank warranty form
D
Make the architect's lunch order the answer for unpriced change work

Why This Is the Correct Answer

When changed work proceeds before final pricing, detailed daily cost records support later adjustment. Other choices do not document the cost of the directed changed work.

Why the Other Options Are Wrong

Option B: Base the unpriced change work response on the original bid recap

In procurement and contracting, Only the original bid recap is the wrong selection for Unpriced change work: the option delays or omits the controlling step.

Option C: Classify the condition as a blank warranty form

The trap in C is A blank warranty form. That selection is wrong because the choice would not get the project to Daily labor, equipment, material, and subcontractor cost records for later pricing, which is the Unpriced change work result verified by the source; Unpriced directed work should be.

Option D: Make the architect's lunch order the answer for unpriced change work

Choice D gives The architect's lunch order. Its specific error: the option does not produce the required Unpriced change work outcome, Daily labor, equipment, material, and subcontractor cost records for later pricing.

Memory Technique

Picture a field note on the jobsite; unpriced change work is solved by the action that leads to Daily labor, equipment, material, and subcontractor cost records for later pricing.

Reference Hint

Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Force-account or directed-change documentation" to confirm that When changed work proceeds before final pricing, detailed daily cost records support later adjustment.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.